This project played a vital role in strengthening water security for the region.
Project value has been adjusted to reflect approximate current-day value as at 2025, based upon industry recognised construction indexation published by Rawlinson.
Delivered a major water storage asset for the South East Queensland water grid, comprising large-scale concrete, structural steel, mechanical and electrical infrastructure.
The reservoir measured 62 metres in diameter and 11 metres high and incorporated 36 internal columns with approximately 1,300m³ of concrete.
A 3,000m² post-tensioned concrete slab was constructed in a single pour, requiring a workforce of 30 concreters.
The reservoir walls were constructed in three full-perimeter lifts, requiring three complete perimeter concrete pours.
Construction incorporated 350 tonnes of reinforcement together with approximately 100 kilometres of steel tendons.
Approximately 90 tonnes of structural steel and metal sheet roofing were installed to fully enclose the reservoir.
Ancillary metalworks included davit arms, ladders, platforms and handrails to support ongoing operation and maintenance activities.
Electrical and telemetry systems were installed to integrate the reservoir into the broader water network.
Associated infrastructure works included access roads, fencing and drainage surrounding the reservoir facility.
This project played a vital role in strengthening water security for the region.
The reservoir measured 62 metres in diameter and stood 11 metres high, supported by 36 internal columns and over 1,300m³ of concrete. Construction highlights included a 3,000m² post-tensioned slab poured in a single operation, three perimeter wall lifts, and installation of 350 tonnes of reinforcement with 100km of steel tendons. The structure was fully enclosed with 90 tonnes of structural steel and metal roofing, complemented by ancillary works such as ladders, platforms, and handrails. Electrical and telemetry systems were integrated, along with external works including access roads, fencing, and drainage.
Despite weather-related challenges, Alder completed the project ahead of schedule through meticulous planning and strict site controls—delivering a critical asset for the region’s water network.
116 Siganto Drive, Helensvale, QLD 4212
153 Racecourse Road, Ascot, QLD 4007
1st Floor, Suite 1, 95 - 101 River Street Ballina, NSW 2478