Stage 5 of the Mooloolaba to Minyama Separated Bikeway introduced a 66-metre, three-span pedestrian and cycle bridge across the environmentally sensitive Mayes Canal, improving connectivity, safety, and reducing traffic congestion.
Project value has been adjusted to reflect approximate current-day value as at 2025, based upon industry recognised construction indexation published by Rawlinson.
Construction adjacent to residential properties, holiday units and commercial areas required detailed planning and stakeholder consideration to minimise community impacts.
Piling activities were redesigned from a barge-based methodology to construction from rock bunds, reducing environmental impacts while mitigating flood and safety risks.
The project delivered a three-span reinforced concrete bridge measuring 66 metres long and 5 metres wide, including shared pedestrian and cycle path approaches.
More than 130 metres of stainless steel architectural balustrading and approximately 70 metres of stainless steel handrail were installed throughout the structure.
Architectural precast concrete parapets featuring wave-pattern panels were incorporated, together with smart lighting capable of changing colours and timing sequences.
The project included construction of 100 linear metres of stone-pitched revetment wall along the adjoining beach and parklands.
Stage 5 of the Mooloolaba to Minyama Separated Bikeway introduced a 66-metre, three-span pedestrian and cycle bridge across the environmentally sensitive Mayes Canal, improving connectivity, safety, and reducing traffic congestion.
The bridge featured a 5-metre-wide shared path, architectural stainless steel balustrades, and pre-cast concrete parapets with wave-pattern detailing. Smart lighting added a dynamic visual element, while stone-pitched revetment walls enhanced the surrounding parklands. Construction required innovative solutions, including delivering piling from rock bunds to minimise environmental impact and mitigate flood risks, all while working within a busy residential and commercial precinct.
Alder Constructions proudly brought this vision to life, blending creativity and technical precision to deliver a landmark bridge for the community.
2019 IPWEA-QNT Excellence Award Winner