Situated on a 17,366m² site within the Aspire Industrial Park, this multi-stage development included the design and construction of an Asphalt Batching Plant and two-storey commercial office building.
Project value has been adjusted to reflect approximate current-day value as at 2025, based upon industry recognised construction indexation published by Rawlinson.
An integrated industrial and commercial facility designed to optimise asphalt production, logistics and business operations within a live operating environment.
Alder managed the full design process for the batching plant and office facility, ensuring both developments met Colas' operational requirements and future growth objectives.
Value-engineering initiatives increased aggregate storage capacity and refined building locations to improve plant productivity and accommodate B-double vehicle movements.
The development included bulk earthworks across three lots, construction of retaining walls and extensive site preparation works for the industrial facility.
Rigid concrete pavements, driveways and plant foundations were designed and constructed to withstand demanding industrial loading conditions.
Comprehensive underground infrastructure was installed across the site, including electrical, communications, water, sewer, security and fire water services.
The project delivered a laboratory, crew room, workshop and wash bay, alongside a two-storey office building containing nine offices, meeting rooms, boardroom facilities and staff amenities.
The office building was constructed adjacent to the asphalt crushing plant and required an RW60 acoustic rating. Collaboration between the project team and specialist consultants achieved the required performance outcome within budget constraints.
Construction was delivered within an operational asphalt plant, requiring careful management of deliveries, concrete pours and interface works while maintaining ongoing site operations.
Specialist hazardous waste management measures and stormwater quality devices were incorporated to support manufacturing operations and environmental compliance requirements.
Regular communication with Colas operational personnel supported project delivery and minimised disruption throughout construction activities.
Situated on a 17,366m² site within the Aspire Industrial Park, this multi-stage development included the design and construction of an Asphalt Batching Plant and two-storey commercial office building.
The Asphalt Batching Plant was tailored to meet the operational demands of Colas’ high-impact manufacturing processes. Alder provided full design management and value-engineered solutions, including expanded aggregate storage, B-Double access, and compliance with environmental and hazardous waste regulations. The facility features a laboratory, crew room, workshop, wash bay, and robust infrastructure such as concrete pavements, retaining walls, and underground services.
Adjacent to the plant, Alder constructed a modern office building with nine offices, meeting and board rooms, kitchen facilities, and a covered walkway connecting to the existing workshop. Despite the challenges of building within an operational asphalt plant, the project was completed ahead of schedule. Acoustic performance requirements were met through a collaborative design approach, ensuring a high-quality, functional workspace aligned with Colas’ growth and operational needs.The Asphalt Batching Plant was successfully delivered following Alder’s development of the Aspire Industrial Park subdivision, where Colas acquired their site.