The project was executed alongside The Star Entertainment Group’s project coordinators and ran concurrently with the Integrated Arrival upgrade, managed by Alder’s civil and infrastructure team.
Project value has been adjusted to reflect approximate current-day value as at 2025, based upon industry recognised construction indexation published by Rawlinson.
A major resort and day spa refurbishment was delivered within a live tourism environment while maintaining continuous public access to surrounding facilities.
Construction was completed within a fully operational resort, requiring detailed safety management and coordination due to the high level of public interface.
The refurbishment included demolition of existing building areas, supported by detailed surveys and identification of existing services prior to construction.
New electrical, air conditioning, plumbing, fire protection and audio-visual systems were installed throughout the upgraded facilities.
New patron amenities, day spa treatment facilities and dedicated treatment rooms were constructed as part of the redevelopment.
A contemporary reception and lobby area was delivered featuring high-quality finishes and upgraded guest arrival spaces.
The project included construction of new function and meeting rooms together with a feature spa within the external events podium area.
External events podium areas were remodelled and fitted out with themed landscaping and upgraded audio-visual infrastructure.
The project was executed alongside The Star Entertainment Group’s project coordinators and ran concurrently with the Integrated Arrival upgrade, managed by Alder’s civil and infrastructure team.
The refurbishment involved the demolition of existing zones, installation of new services including electrical, HVAC, plumbing, fire protection, and AV systems, and the construction of new amenities and day spa treatment rooms. A luxurious reception and lobby area was created with premium finishes, complemented by new function and meeting rooms, and a feature spa on the external events podium. The podium area was also remodelled with themed landscaping and high-quality audio-visual integration.
Given the proximity to a busy public thoroughfare and pool, the project demanded meticulous planning, dual shifts, and night works to meet tight deadlines while maintaining uninterrupted access for patrons. The result was a seamless transformation that elevated the resort’s guest experience.